Dubai Metro Blue Line building has reached 12 per cent completion, with greater than 3,000 staff deployed throughout a number of websites as Dubai’s Roads and Transport Authority advances certainly one of its most strategic transport initiatives.
The road is scheduled to open according to the authorized programme on September 9, 2029.
Mattar Al Tayer, Director Normal, Chairman of the Board of Govt Administrators of the Roads and Transport Authority (RTA), chaired the Dubai Metro Blue Line Discussion board assembly on the Precast Concrete Manufacturing and Storage Manufacturing facility in Worldwide Metropolis, attended by the heads of the Dubai Metro Blue Line Mission Consortium.
The assembly introduced collectively the chairmen of the boards of MAPA, Limak and CRRC Hong Kong, together with the heads of the consultancy and contracting firms delivering the venture and a number of other RTA chief govt officers.
The Discussion board convenes frequently as a part of RTA’s technique to observe progress and take needed selections to make sure compliance with the authorized venture schedule.
Dubai Metro Blue Line information
Through the assembly, the Discussion board reviewed venture updates and progress. Greater than 3,000 staff, supervised by 500 engineers and specialists, are presently engaged on the venture throughout 12 places.
The consortium has accomplished greater than 4.6m working hours throughout building websites, whereas general venture completion has reached 12 per cent.
Progress is anticipated to rise to 30 per cent by the tip of 2026, with the venture set to open in September 2029 as deliberate.
Al Tayer and Discussion board members inspected the ready-mix concrete casting plant, which varieties a part of a first-of-its-kind strategy for an RTA rail venture.
The Dubai Metro Blue Line is the primary rail venture applied by RTA to incorporate two ready-mix concrete batching crops and two precast concrete storage services situated in Al Ruwayyah 3 and Worldwide Metropolis.
Dubai Metro Blue Line building
Discussion board members had been briefed on the manufacturing capability of the services. The ready-mix concrete batching plant in Al Ruwayyah 3 produces 200 cubic metres of ready-mix concrete, whereas the viaduct precast manufacturing yard delivers between 10 and 12 viaduct segments per day.
In Worldwide Metropolis, the ready-mix concrete batching plant produces 120 cubic metres of ready-mix concrete, and the precast tunnel rings manufacturing unit produces 12 rings per day.
Transport improvement
The Dubai Metro Blue Line spans 30 km and consists of 14 stations, making it certainly one of RTA’s key strategic initiatives. The road hyperlinks the Crimson and Inexperienced Strains of the Dubai Metro and serves areas with an estimated inhabitants of round a million by 2040.
The Blue Line will present direct journeys to Dubai Worldwide Airport in 20 minutes and helps the aims of the Dubai 2040 City Grasp Plan by connecting the fifth city space to the metro community.
It additionally helps the 20-minute metropolis idea by enabling entry to greater than 80 per cent of providers inside 20 minutes of journey.
As well as, the venture helps Transit-Oriented Improvement (TOD), advances the Dubai Financial Agenda (D33), will increase land and property values round stations by as much as 25 per cent, and reduces site visitors congestion by 20 per cent alongside the corridors served by the Blue Line.